Seeing some good progress!  We're getting really close however I can't place my finger on a delivery date.  The slide production fluctuates from 1,000-1,500 per day a range of 38 to 57 days, which we're 17 days in.

SLIDES

The slides boxes have arrived and the packaging has begun. The image below are 7 slide boxes.  All the slides will be pre-packaged into 7 and 10 slide boxes before being packaged into larger bundle boxes that will include the folder, brackets and the number of slides in your reward level.  

 

FOLDER 

The folders are 85% done and production will be complete next week.  The image below are the large side panels of the folder.

The following image is the smaller bottom panel of the folder. 